Why pay applications get rejected: a pre-submit checklist
A rejected pay app usually costs a resubmission, and often a whole payment cycle. Most rejections come from a short list of problems you can check in a few minutes before you send.
The numbers
- The summary doesn't tie to the continuation sheet. Line 3 (contract sum to date) must equal the total of column C, line 4 must equal the total of column G, and retainage on line 5 must match column I. In a spreadsheet this breaks when a row is added outside a SUM range or a value is pasted over a formula.
- “From previous application” is wrong. Column D on every line should equal column G from your last approved application, not the version you first sent if the GC revised it. Line 7 is the total certified on earlier applications, not the total you were paid.
- A line is billed over 100%. Completed and stored to date (G) can't exceed the scheduled value (C). If the scope grew, it needs an approved change order, not a bigger percentage.
- Billing ahead of the work. Percentages higher than the work in place, or front-loaded early lines, get cut back at the walk-through. Bill what the GC's superintendent will agree is in place.
- Retainage at the wrong rate or base. Use the rate in your subcontract, applied to all completed work (D + E), not just this period, plus the stored-materials rate on column F. If your contract reduces retainage at a milestone, apply it the way the contract says. See what is retainage.
- Change orders billed before approval, or a change order on line 2 with no matching continuation-sheet line. See change orders on pay applications.
The paperwork
- Lien waivers. Many GCs want a conditional waiver for this payment and an unconditional waiver for the last one, and the amounts must match the pay app. Use the waiver forms your contract and state require.
- Stored materials backup. Invoices, proof of delivery or storage, and sometimes insurance or photos for column F. See billing for stored materials.
- Other attachments the GC or lender asks for: certified payroll on public work, an insurance certificate, updated schedules.
- The right form. Some GCs require their own form or the official AIA documents. If so, copy your figures onto it.
The basics
- The application number and period to date are right and follow on from last month.
- It goes in before the GC's cut-off date. Late applications usually wait for the next cycle.
- It's signed, and notarized if the contract asks for it.
What Drawsheet checks for you
Drawsheet does the arithmetic and flags lines billed over 100%, a contract sum that doesn't match the schedule of values, billing on a line with no scheduled value, negative work to date, duplicate item numbers, a missing billing period, and an application number above 1 with nothing in “from previous application”. It can't check the paperwork, the GC's deadlines or whether a change order is approved. That part of the list is yours. Try it with sample data to see the checks, or see pricing for unlimited lines and the Excel workbook.